RENOVATION SCHEDULE
Dates are subject to change due to unforseen circumstances.
NOVEMBER 2025
-
Ongoing (Nov 2025): Crews work on the second half of Span 4.
-
Late Nov 2025: Begin sandblasting and painting on Span 3 (south toward downtown) immediately after Span 4 completion.
-
Mon, Nov 3–Tue, Dec 2, 2025: River Street reduced to one lane, managed by the temporary signal setup used earlier this year.
-
Nov 3–Dec 2, 2025: Install a new temporary boardwalk over River Street; the River Street sidewalk remains open.
-
Mid-Nov 2025: Relocate sandblasting to the south side; stage along Riverfront Parkway under the bridge.
-
Through bridge completion: Maintain Coolidge Park lay-down area for wood, water line, and electrical work.
2026 PROJECTIONS
-
Early 2026: Install remaining conduit on Span 5 through the Frazier Avenue approach.
-
By Jan 31, 2026: Finish wood installation on Span 6 to Frazier Avenue.
-
Then: Shift wood installation to the south half of the bridge toward downtown.
SEPTEMBER 2026
The bridge renovation will be complete and bridge will reopen.