Below is the timeline for the rehabilitation of Walnut Street Bridge.

RENOVATION SCHEDULE

Dates are subject to change due to unforseen circumstances.

May-September 2026

  • Continued removal of old wood in spans 1-2 closest to the south shore,  replace deficient steel, and install new decking and sidewalk boards.

  • Install remaining conduits, pull wiring, install light fixtures and cameras

  • Construct concrete platform adjacent to Holmberg Bridge, install electrical panels

  • Additional ADA improvements 

  • Re-install name plates

  • Install bridge roadway drainage system

  • Remove work platforms from below spans 1-6 and lay down areas, and repair and landscape park grounds.

  • Install numerous amenities including  benches, flower pots, trash cans, pet waste stations, historic signs

SEPTEMBER 2026

Completion is on target for the end of September, complete with a large celebration. Details are in the works and additional announcements to come! Events will be followed by the Ironman event on September 27th.