RENOVATION SCHEDULE
Dates are subject to change due to unforseen circumstances.
May-September 2026
-
Continued removal of old wood in spans 1-2 closest to the south shore, replace deficient steel, and install new decking and sidewalk boards.
-
Install remaining conduits, pull wiring, install light fixtures and cameras
-
Construct concrete platform adjacent to Holmberg Bridge, install electrical panels
-
Additional ADA improvements
-
Re-install name plates
-
Install bridge roadway drainage system
-
Remove work platforms from below spans 1-6 and lay down areas, and repair and landscape park grounds.
-
Install numerous amenities including benches, flower pots, trash cans, pet waste stations, historic signs
SEPTEMBER 2026
Completion remains on track for the end of September, with the official reopening date to be announced soon.