RENOVATION SCHEDULE
Dates are subject to change due to unforseen circumstances.
March 2025
-
Sandblasting, priming and painting have been completed on all spans.
-
Half of the decking has been replaced
-
Electrical work is being completed on the half of the bridge that has new decking
-
Structural work continues on the half of the bridge that does not yet have new decking.
-
Project is on track for late September 2026 completion.
SEPTEMBER 2026
The bridge renovation will be complete and bridge will reopen.